济南市长清区浩博新型建材厂http://www.sdjnhbjc.com
Ji'nan Haobo District of Changqing City, new building materials factory http://www.sdjnhbjc.com
grc线条如果维护不当或者其他原因也会导致其出现漏水的现象,
GRC lines if maintained properly or other reasons will lead to the phenomenon of water leakage,
现场的处理:
1、按照原设计图集施工,GRC线条顶面做聚合物砂浆抹面并刷防水涂料;
2、拆除GRC线条,粘贴苯板,然后网格布施工,腻子层施工,涂料层施工;
Field treatment:
1, according to the original design of GRC line construction, the top surface of polymer mortar and do waterproof paint brush;
2, remove the GRC line, and then paste the benzene board, grid construction, putty layer construction, coating layer construction;
现场对GRC线条进行网格布翻包施工,腻子层施工,涂料层施工;考虑到现场实际情况,最终选择第三种方案。 门式脚手架的搭设:以门架、交叉支撑
、连接棒、挂扣式脚手板或水平架、锁臂等组成基本结构,再设置水平加固杆、剪刀撑、扫地杆、封口杆、托座与底座,并采用连墙件与建筑物主体结
构相连的一种标准化钢管脚手架。 门架、交叉支撑、脚手板、连接棒、锁臂、水平架、水平加固杆、剪刀撑、扫地杆、封口杆、底座、连墙件、栏杆、扶手。
The scene of GRC lines of mesh construction over packet, putty layer construction, construction of the coating layer; taking into account
the actual situation, the final choice of the three schemes. Gate scaffolding erection: to the door frame, cross bracing, a connecting rod,
hanging button scaffold boards or horizontal planes, a lock arm forms a basic structure, then set the horizontal reinforcement bar, scissors,
a sweeping rod, sealing rod, a bracket and a base, and adopting the connecting pieces of the wall and main structure of the building is
connected with a standard of steel pipe scaffold. The door frame, cross bracing, scaffolding, connecting rod, a lock arm, a horizontal frame,
a horizontal reinforcement bar, scissors, a sweeping rod, sealing rod, a base, a wall connecting piece, railings, handrails.